Second drilling campaign
Third drilling campaign
Darwin selected as LNG Plant location(2008)
Commencement of onshore and offshore FEED work (2009)
Application for Environmental Approval
Application for Production Licenses
Granted environmental approval from Federal and Northern Territory governments
Liquefied Natural Gas (LNG) sales agreement signed
Offshore EPC / Onshore EPC
Final Investment Decision Executed (January 2012)
Groundbreaking Ceremony of LNG Plant (May 2012)
Project Financing Arrangements Completed (December 2012)
FPSO Keel Laid (February 2014)
Construction Milestone Reached for World's Largest CPF Semi-submersible Platform (April 2014)
Project Half Way Mark Reached (June 2014)
Commencement of 889 Kilometer Pipelay (June 2014)
Floating Production, Storage and Offloading (FPSO) Hull Launched (July 2014)
Completion of Dredging in Darwin, Australia for Shipping, Gas Export Pipeline (August 2014)
Commencement of Development Drilling (February 2015)
Central Processing Facility (CPF) Launched (September 2015)
Completion of Offshore Pipelay (November 2015)
Central Processing Facility (CPF) Sailed Away (April 2017)
Commencement of gas production from the wellhead (July 2018)
Commencement of LNG and condensate shipment (October 2018)
Commencement of LPG shipment (November 2018)
100th LNG cargo shipped (November 2019)
Financial completion achieved (December 2019)